Campaign Project Updates

Updates throughout the duration of the campaign will be added below, as we embark on the most ambitious project in Brighton Grammar's history.
02 March 2023

Soil excavation

Headmaster site visit

02 March 2023

Construction is progressing really well, with soil excavation the main focus for the team at Vaughan Constructions, the builders for our Centre for Science, Creativity and Entrepreneurship. The Headmaster, Ross Featherston visited the site today to gain an insight into the progression of the project. A large amount of soil has been removed and the sheer size of the land is discernible as St Andrew’s Church spire stands tall in the distant background. Brighton Grammar School is looking forward to the strengthened connection that this Centre will enable with St Andrew’s. The next step in the construction phase will be piling.

 

Construction is progressing really well, with soil excavation the main focus for the team at Vaughan Constructions, the builders for our Centre for Science, Creativity and Entrepreneurship. The Headmaster, Ross Featherston visited the site today to gain an insight into the progression of the project. A large amount of soil has been removed and the sheer size of the land is discernible as St Andrew’s Church spire stands tall in the distant background. Brighton Grammar School is looking forward to the strengthened connection that this Centre will enable with St Andrew’s. The next step in the construction phase will be piling.

 

Soil excavation

Headmaster site visit

02 March 2023

06 February 2023

External Hoarding

Stakeholder graphics and renders

06 February 2023

The external hoarding on St Andrews St has been updated over the last week. The update includes graphics of the key stakeholders involved in the construction of our Centre for Science, Creativity and Entrepreneurship and architectural renders showcasing the building.

This addition comes as we move forward with the construction in coming weeks, with soil excavation and piling to commence now that the site clearing is complete.

The external hoarding on St Andrews St has been updated over the last week. The update includes graphics of the key stakeholders involved in the construction of our Centre for Science, Creativity and Entrepreneurship and architectural renders showcasing the building.

This addition comes as we move forward with the construction in coming weeks, with soil excavation and piling to commence now that the site clearing is complete.

External Hoarding

Stakeholder graphics and renders

06 February 2023

19 January 2023

Demolition Commencement

External demolition and site protection

19 January 2023

Works have been steadfast this month and viewable from St Andrews St.

The Science wing has been completely demolished with works underway on the remaining structure.

A partial gantry has been established and further hoarding installed across the old tennis courts. Pedestrian pathway access along this section has been diverted while these works are completed.

There will continue to be action over the coming month with machinery, earthworks and clearing continuing.

Works have been steadfast this month and viewable from St Andrews St.

The Science wing has been completely demolished with works underway on the remaining structure.

A partial gantry has been established and further hoarding installed across the old tennis courts. Pedestrian pathway access along this section has been diverted while these works are completed.

There will continue to be action over the coming month with machinery, earthworks and clearing continuing.

Demolition Commencement

External demolition and site protection

19 January 2023

22 December 2022

Demolition progression

Internal strip out

22 December 2022

Internal strip out of the old science building is well underway with works progressing steadily in anticipation for completion by the end of 2022 and ready for demolition of the old library to commence. Over the next 1-2 months you will begin to see the following:

-Delivery of machinery and materials.

-Demolition of existing school buildings, tennis court facilities and fencing.

-Installation of footpath protection gantry and set up of loading bay zones.

-Earthworks and Retention system commencement including concrete trucks and the pouring of concrete.

Internal strip out of the old science building is well underway with works progressing steadily in anticipation for completion by the end of 2022 and ready for demolition of the old library to commence. Over the next 1-2 months you will begin to see the following:

-Delivery of machinery and materials.

-Demolition of existing school buildings, tennis court facilities and fencing.

-Installation of footpath protection gantry and set up of loading bay zones.

-Earthworks and Retention system commencement including concrete trucks and the pouring of concrete.

Demolition progression

Internal strip out

22 December 2022

30 November 2022

Demolition Preparation

Hoarding Installation

30 November 2022

In readiness for demolition works, the hoarding has been installed on the south side of the Senior School Quad and exposed boundaries of the construction site.
Low impact, preparative internal demolition works have begun and external demolition will become visible over the coming weeks.

In readiness for demolition works, the hoarding has been installed on the south side of the Senior School Quad and exposed boundaries of the construction site.
Low impact, preparative internal demolition works have begun and external demolition will become visible over the coming weeks.

Demolition Preparation

Hoarding Installation

30 November 2022

14 November 2022

Signing of Contracts with Builder

Vaughan Constructions

14 November 2022

Exciting news for the Centre for Science, Creativity and Entrepreneurship with the signing of contracts between Brighton Grammar, St Andrew’s Brighton and the appointed builder for the project, Vaughan Constructions. This significant juncture in the project will allow for works to begin very soon, including the installment of hoarding around the site for demolition.

Thank you to Brighton Grammar’s COO, Michael Arceri and St Andrew’s Brighton Vicar, Ian Morrison for their diligent work and cooperation in this important progression for the project.

Exciting news for the Centre for Science, Creativity and Entrepreneurship with the signing of contracts between Brighton Grammar, St Andrew’s Brighton and the appointed builder for the project, Vaughan Constructions. This significant juncture in the project will allow for works to begin very soon, including the installment of hoarding around the site for demolition.

Thank you to Brighton Grammar’s COO, Michael Arceri and St Andrew’s Brighton Vicar, Ian Morrison for their diligent work and cooperation in this important progression for the project.

Signing of Contracts with Builder

Vaughan Constructions

14 November 2022